EIP is awarded two new contracts in Colombia
EIP Colombia signed two new contracts with ISA (INTERCOLOMBIA):
The Extension of the 500/220 kV Copey Substation, with a transformer bay of 3 auto-transformers of 150 MVA each, for the specialities of civil construction, electric installation and tests, with a 10 months execution period and the Extensions of Beania and Ibagué Substations with a line bay of 230 kV in each, on a EPC basis and a 14 months execution period.